- Preparation of detailed checklists covering all aspects of pre commissioning and commissioning activities.
- Finalise the list of documents required for the pre check.
- Pre commissioning audits covering process licensor’s requirements, process and mechanical integrity of the plant, compliance to OISD, PESO requirements.
- Preparation of operating manuals and commissioning procedures based on the licensor and OEM’s recommendations.
- Preparation of schemes for flushing and Hydro test and list all resources, utilities, consumables, work force requirements.
- Preparation of all SOPs for operation and maintenance, inspection, equipment, electrical Instrumentation, DCS/PLCs etc.
- Safety requirements and checks.
- Prepare Normaland and Emergency shutdown procedure, Emergency handling procedure.and training of the people for the same.
- Training of the Engineers and workmen for the start up, Normal operation and Emergency handling.
- Checks for all the equipment internals, Column internals, Catalyst loading etc.
Safety checks as per Licensor, Engineering Consultant, Equipment vendors etc for both visible and invisible safety concerns.