• Preparation of detailed checklists covering all aspects of pre commissioning and commissioning activities.
  • Finalise the list of documents required for the pre check.
  • Pre commissioning audits covering process licensor’s requirements, process and mechanical integrity of the plant, compliance to OISD, PESO requirements.
  • Preparation of operating manuals and commissioning procedures based on the licensor and OEM’s recommendations.
  • Preparation of schemes for flushing and Hydro test and list all resources, utilities, consumables, work force requirements.
  • Preparation of all SOPs for operation and maintenance, inspection, equipment, electrical Instrumentation, DCS/PLCs etc.
  • Safety requirements and checks.
  • Prepare Normaland and Emergency shutdown procedure, Emergency handling procedure.and training of the people for the same.
  • Training of the Engineers and workmen for the start up, Normal operation and Emergency handling.
  • Checks for all the equipment internals, Column internals, Catalyst loading etc.

Safety checks as per Licensor, Engineering Consultant, Equipment vendors etc for both visible and invisible safety concerns.